Re: Actual cost calculation and Revaluation for Cost object (KSS2, KSII, KON2)

$
0
0

Hello Ajay-san,

 

Thank you very much for the reply. Please let me ask following point.

 

Now I am facing following error message in KSS2. I have already maintained fixed price in KP26. But the error is still being shown up.

 

No target costs in target cost version 0 - missing plan for ATY

Company xxx/Cost centre xxx/ACTYxx

 

Does it mean we need to input planned Qty or planned amount for cost element?

 

And if the process finishes successfully, which field should have amount? (Target cost and Control cost?)

 

Thanks and Best regards,

Satoe